BUDGET REPORTS PeopleSoft has several delivered Budget Reports.
BUDGET STATUS REPORT Navigation: Commitment Control à Review Budget Activities à Budget Reports à Budget Status
When running processes or reports, PeopleSoft usually requires the user to create a process name (often called a Run Control ID). To add a new Inquiry Name, select the
Complete the Business Unit (SALIS or SUFND) and Ledger Group (CC_DEPT or CC_PROJ). CC_DEPT is used for to review department budgets. CC_PROJ is used to review project budgets. Select
Complete the appropriate department number or project number value. BUDGET REPORTS Select The user could also decide to create a Run Control ID specific to that department or project value. Then no adjustments to the department or project number will need to be made within the Run Control ID. Select The following page appears:
Complete the Server Name using the “drop down arrow” and selecting PSNT. Everything else should be automatically filled by PeopleSoft. Note that the report format is PDF. This will require that
the user has installed Adobe Reader. Installation of the Adobe Reader can be
found at http://www.adobe.com/products/acrobat/readstep2.html
Select The following page appears:
Note that a Process Instance number appears. Select
The following page appears:
The process will likely have a Run Status of “Queued”
and it will progress (hopefully) to “Success”. The user can select
The actual report can be found by selecting the View Log/Trace link. The Message Log link provides job information identifying the processes run and whether such processes were successfully completed. An example of such follows:
The following page appears:
Select the report link above and the report will open. An example of the Budget Status Report follows:
LEDGER DETAILS REPORT The Ledger Details Report summarizes total budget, encumbrances and expenses for each commitment control budget of a department or project. The Available Budget is also calculated for each commitment control budget. Navigation: Commitment Control à Review Budget Activities à Budget Reports à Ledger Details
The user can use the existing Run Control ID (created for the “Batch Status” Report) or add a new one. Select Once an existing or new Run Control ID is selected, the following page appears:
Complete the Business Unit (SALIS or SUFND) and Ledger Group (CC_DEPT or CC_PROJ). CC_DEPT is used for to review department budgets. CC_PROJ is used to review project budgets. Select Complete the appropriate department number or project number value. Select Select Complete the Server Name using the “drop down arrow” and selecting PSNT. Everything else should be automatically filled by PeopleSoft. Select Select Select Once the job status equals Success, select the Details link and then the View Log/Trace link. Select the report link and open the report.
The following report is created.
BUDGET TRANSACTION DETAIL REPORT
Navigation: Commitment Control à Review Budget Activities à Budget Reports à Budget Transaction Detail
The user can use the existing Run Control ID (created for the “Batch Status” Report) or add a new one. Select Once an existing or new Run Control ID is selected, the following page appears:
Complete the Business Unit (SALIS or SUFND) and Ledger Group (CC_DEPT or CC_PROJ). CC_DEPT is used for to review department budgets. CC_PROJ is used to review project budgets. Also enter a timeframe (Date From and Date To). Select Complete the appropriate department number or project number value. Select Select Complete the Server Name using the “drop down arrow” and selecting PSNT. Everything else should be automatically filled by PeopleSoft. Select Select Select Once the job status equals Success, select the Details link and then the View Log/Trace link. Select the report link and open the report.
The following report is created.
|