A.
Project Administration: Outline of Responsibilities
Once the award notice and any special conditions have been
reviewed and accepted by the P.I., Chair and
Dean of the University, all paperwork will be forwarded by the Grants
Office to the Fiscal Grants
Management Office for account setup. The Project Director will meet with
the Fiscal Grants Office and
bears primary responsibility for the administration
of the project. Project Directors should handle project
responsibilities
in exactly the same way that they handle
their regular responsibilities.
In other words, any
problems with the administration of the project
should be handled by the
Project Director with the assistance
of the Chairperson of the Department in which the Project Director
works. Problems that cannot be resolved
at this level should
be referred to the appropriate Dean.
The Office of Grants and Sponsored Research is a part of the
Salisbury University Office of the Provost and,
as such, has a strong interest in scholarly research, curriculum reform
and community outreach. The
Grants
Office can help Project Directors solve problems that
they may encounter in conducting their grants by
interpreting
grant requirements, demystifying agency jargon and explaining
University grant policies.
Jackie Eberts, Director
of Fiscal Grants Management is part of the University's
Business and Finance
Office and is responsible, along with the
Project Directors, academic administration and other administrative
offices of the University, for monitoring compliance with grant
provisions. Under all circumstances, the
University complies
with the Federal Office of Management and Budget (OMB) "Uniform
Administrative
Requirements for Grants and Cooperative Agreements
with
Institutions of Higher Education, Hospitals and
Other Nonprofit
Organizations" (OMB Cir. A-110), "Cost Principles for Educational
Institutions"
(OMB Cir. A-21) and "Audits of States, Local Governments and Non-Profit
Organizations"
(OMB Cir. A-133). All financial reporting
regarding program income, payment requirements, revisions of
financial
plans, etc. will follow OMB guidelines.
In addition, the Grants Office and the Fiscal Grants Management
Office have primary responsibility for
two activities:
1. Liaison With Funding Agencies
The Grants Office will act as the point of contact between the funding
agencies and the University for both
pre-award and post-award
communications. Contact with funding agencies for all purposes,
both pre-award
and post award, must be cleared through
the
Office of Grants and Sponsored
Research. Copies
of all
documents
submitted to funding agencies must also be submitted
to the Grants Office. All financial
documents/reports will be approved
by the
Fiscal Grants Management
Office.
2. Coordination Among Salisbury University Offices
The Grants Office may coordinate University actions on those
issues which require the participation of many
offices within
the University. For example, preparation and submission of final
reports usually require the
participation of the Project
Director,
that person's supervisor(s), and the Fiscal Grants Management Office.
Therefore, this task will be coordinated through the Grants
Office.
Return to Top
B.
Project Administration: How To
Once the grant project is funded, the responsibility for running
the project rests with the Project Director.
All matters dealing
with the expenditure of funds (procurement, invoicing, personnel
contracts) should be
addressed by the Fiscal
Grants Management Office.
1. How to Spend Grant Project Funds
Funds can only be spent on a grant for which a binding notice
or a grant award contract from the funding
agency has been
received
by the University and
the following have all occurred:
a. The University has accepted
the grant.
b. Notice of the grant award and the approved operating
budget have been sent from the Office of
Grants and Sponsored Research and been received by
the Fiscal Grants Management Office.
c. Required grant accounts have been established.
d. The official grant period has begun.
2. Prohibitions on Expending Grant Funds
a. Funds may not be spent on
activities not allowed by the funding agency.
b. Funds may not be spent on activities not specified
in the grant budget unless this has been cleared
with the awarding agency and that agency has
given written permission for the change.
c. No funds from Departmental or other non-grant
accounts may be expended on grant activities. It is
not possible to use other accounts to fund grant
activities and then "transfer" the costs to the grant
account or otherwise
"cover" these expenditures.
d. In most instances University personnel working on
grant projects may not work on an overload basis
at the same time.
e. All expenditures will be made in accordance with
federal guidelines established in
OMB
Circular A-21
and/or
EDGAR.
f. Indirect Costs may not be spent on grant
activities. See SU's Policy on
Indirect Costs.
g. Foreign travel is not allowed under most grant
contracts unless approved in the awarded grant/contract.
Return to Top
C.
Contracts Resulting from Grant Proposals
In many instances a successful grant proposal, by itself, becomes
the guiding document for a grant-funded
project. In other
instances
the successful grant proposal is just the first step in developing
a project contract.
Contracts resulting from successful grant proposals must be approved
by the Office of Grants and
Sponsored Research and
signed by the appropriate University
authority. This protects both the University
and the Project
Director.
A project contract must be approved in the same fashion as a
grant proposal. The same approval form is used.
Return to Top
D.
Program or Budget Modifications
Significant changes in the grant program or budget specifications
shall not be made without the prior approval
of the
granting
agency. Formal requests to the funder for programmatic or budget
modifications will be
submitted via the Grants Office after consultation with the P.I. and Fiscal
Grants Management Office.
Any changes in a grant project which affect budgeted expenditures
should be carefully considered. Total
budgets must never
be exceeded.
Individual budget lines should not be exceeded without the prior
knowledge
and approval of the Director
of
Grants and Sponsored Research, the Fiscal
Grants Management Office, and
the awarding agency.
Under no circumstances may transfers be made from an approved
project line item to a use not allowed
by the granting agency.
Under no circumstances may transfers be made from the institutional
support side
of the budget to the grant request side of the budget
or vice versa.
In all circumstances, Project Directors must assure that all
the funds allotted to their project are spent
according to the
stipulations in the contract or other agreement governing a grant
project.
Return to Top
E.
Project Reporting
Project Directors are responsible for preparing and submitting
whatever project reports are required by
the funding agency.
Copies of all reports must be submitted to the Grants Office
as well. Interim and final
narrative reports may be required.
The Project Director must read all the documents outlining project
reporting responsibilities and follow the procedures.
In some instances, fiscal reports on projects may be prepared
by the Fiscal Grants Management Office. In
all cases, the Fiscal
Grants Management Office must approve any fiscal/financial reports
before submission
to the awarding agency. The Project Director
is responsible for informing the Fiscal Grants Management
Office
of all expenditures on grant projects. The Fiscal
Grants Management
Office provides a monthly
financial report for each project.
If the funding agency requires return of unexpended funds at
the end of the grant period, the Fiscal Grants
Management Office
will authorize the Accounts Payable Office to prepare a reimbursement
check to the
funding agency. This will occur only after
all final
financial reports have been reviewed and approved for
submission
to the awarding agency. Many private foundations
are not as strict
about this. Nevertheless,
Project Directors should make every
effort to expend all the funds allotted to their
project within
the
contract period.
Return to Top
E.
Project Evaluations
In those circumstances where an independent, outside evaluation of a grant
project must be conducted, Project
Directors are responsible for arranging
that this be done.
Project Directors should keep in mind that sufficient time must be allowed
for the evaluators to review the
project, prepare a
report, and submit it to
the University and then for the University to submit it to the funding
agency. The results of the evaluation should be addressed in the report.
This requires that the evaluation be
completed early enough that the results
will be received in time for the Project Director to review them and
incorporate this in the final report.